1985
COPYHOLD JUNCTION
6th NOVEMBER 1985
INVOLVING BRIGHTON DRIVERS
BRIAN BATCHELOR & PAUL EDWARDS
Extracted and adapted from the M.O.T. inquiry by Major P.M. Oliver
On a clear but windy night the 01:00 Victoria to Brighton electric multiple unit passenger train, 2A18, consisting of four coaches, driven by Brighton Driver Brian Batchelor, which was travelling in a Down direction over the Up line, passed T335X at danger and collided head on with the 01:35 Brighton to Victoria, electric multiple unit train 2A19, which was driven by Brighton Driver Paul Edwards. This train was travelling in the Up direction on the Up Main line prior to crossing over to the Down Main line in the Up direction and was reversibly signalled. The collision caused considerable damage to both trains but
neither train was de-railed.
The emergency services were summond immediately and, on arrival began to convey the injured to hospital. In all 40 persons were injured of whom 39 attended hospital for treatment, but the majority only suffered minor injuries and were released after treatment. The guards of the two trains and along with 11 passengers were detained in hospital.
Following removal of the damaged coaches, the Up and Down Main lines were re-opened for traffic at 08:30 and 08:54 the same morning following which trains ran under caution whilst the signalling was being fully tested. Normal service resumed at 15:30 on the same day.
Description
The Site
Copyhold Junction is approximately 1,600 yards north of Haywards Heath Station and 9,300 yards south of Balcombe Tunnel Junction. The line between the two junctions consists of two tracks, each junction enabling all trains to be routed from Up to Down line and vice versa. The south end of Copyhold Junction has additional crossovers to enable trains on the the Up and Down Main Lines to be diverted to the Up and Down Loop lines through Haywards Heath station. The north end of Balcombe Tunnel Junction has additional switches and crossings to enable trains to be routed between the two lines south of the junction and the four lines leading to Three Bridges and the north. All lines lines are electrified on the conductor rail system at 750 volts DC. The maximum speed on the Up an Down lines in the Up and Down direction is 90 m.p.h. but the maximum permitted speed on the Up and Down direction and vice versa is limited to 75 m.p.h. The maximum permitted speed through the crossover at both junction is 20 m.p.h.
The Signalling
The signalling from Brighton to north of East Croydon on the Brighton - Victoria Main Line is controlled from Three Bridges Signal Box. All signals in the Haywards Heath, Copyhold Junction and Balcombe Tunnel Junction area are four aspect colour light. Signalling in the Haywards Heath and Copyhold Junction area is controlled from the main signal box over a time division multiplex system through a relay room at Haywards Heath. Signalling in the Balcombe Tunnel Junction area is controlled directly from Three Bridges Signal Box.
An important feature of the signalling over the stretch of line between Balcombe Tunnel Junction and Copyhold Junction is the presence of reversible signalling on both lines. Thus at Balcombe Tunnel Junction trains travelling on the Down Main or Down Slow can be routed along the Up line provided that the line to Copyhold is clear. Similarly an Up train approaching Copyhold Junction on the Up Main or Up Loop line can be routed onto the Down Main line in the Up direction. This facility, which also exists from south of Haywards Heath to Preston Park, is fully signalled to enable scheduled trains to be reversibly signalled if this assists in the regulation and control of trains. Its main use, however is during engineering works or following other emergencies such as the breakdown of trains. At the time of the accident the only booked trains using the reversible working between Balcombe Tunnel Junction and Copyhold Junction were the 01:00 from Victoria to Brighton and the 01:35 from Brighton to Victoria, the two trains involved in the head-on collision. The purpose of this working was to keep Victoria and Brighton drivers familiar with the reversibly signalled routes and the equipment in working order.
EVENING ARGUS COLLECTION
The Trains
The 01:00 Victoria - Brighton passenger train, 2A18, consisted of one 4-car train electric multiple-unit, No.7390 of Class 421 (4CIG). The leading coach was a driver trailer composite, followed by a motor brake second, a trailer second and a driver trailer composite. The 01:35 Brighton - Victoria passenger train, 2A19, consisted of one 4-car electric multiple-unit, No.7724, of Class 423 (4VEP). The leading coach was a driver trailer composite, followed by a trailer second motor brake second and a driver trailer composite. Both units were of all steel construction built in 1971 and 1967 respectively. The coaches within each unit were permanently coupled with buckeye couplings. Both units were fitted with electro-pneumatic and Westinghouse brakes and had B.R. standard A.W.S. the overall lengths of the trains were 264ft 10ins and 265ft 41/2 in respectively and their weighs were 145.90 ton and 150.45 ton. The total brake force of each unit was approximately 88% of their tare weight.
Damage to the trains
The damage to the two trains fell into two categories, that to the under frames and that to the interior of the coaches. The underframes suffered most damage at the ends of the coaches where the impact had buckled them. There was also much damage to the draw gear and the centre casting housings on the motor coaches indication the very heavy impact between the two trains.
The damage of each coach of the trains ay be summarised as follows:-
01:00 Victoria - Brighton Unit 7390
4th Coach 76811
Moderate bogie, under frame and interior fitting damage
3rd Coach 71058
Moderate body, interior and bogie damage, serious damage to under frame
2nd Coach 62378
Moderate bogie damage, severe under frame damage, serious damage to body and interior fitting
1st Coach 76740
Severe bogie, under frame, body and interior damage
01:35 Brighton - Victoria Unit 7724
1st Coach 76339
Serious bogie and severe under frame, body and interior damage.
2nd Coach 70843
The ‘B’ end of this coach took much of the force of the impact. The under frame was distorted 24-30in downwards in contact with the bogie. The headstock, sole bars and longitudinals, were all badly buckled. There was very sever body damage at the ‘B’ end of the coach and in ‘K’ compartment there was severe interior damage throughout.
3rd Coach 62185
Slight bogie damage, severe under frame damage, serious and interior damage.
4th Coach 76340
Serious under frame damage, moderate body and interior damage
Damage to signalling equipment and permanent way
There was no damage to the permanent way, but the ‘A’ end of No.1783 points was damaged by the being run through by the Victoria - Brighton train when the points were set ‘reverse’ for the Brighton - Victoria to travel from the Up main line to the Down Main line in the Up direction. The closed switchblade was found slightly opened and the clamp lock hook had been stretched by about an inch.
Evidence
Signalman M.F.J. Meade booked on duty at Three Bridges signal box at 21:15 on 5th November, 1985, controlling Panel 5 which covers the section of the railway from Balcombe Tunnel to south of Keymer Junction. He had no troubles concerning the signalling of any trains on his panel until 01:55 on 6th November. At 01:53 both the Victoria - Brighton, 2A18 and the Brighton - Victoria, 2A19, are time-tabled to arrive at Haywards Heath Station, but the former train was running two or three minutes late and, in order to avoid delay to the Up train, 2A19, he decided to give this train precedence in crossing at Copyhold Junction. Thus route was st for the Down train, 2A18, from Balcombe Tunnel Junction over the Up line in the Down, reversibly signalled, direction to Signal T335X at dander. Meade said that he set for 2A19 from Haywards Heath along the Up main to Junction T332 and thence over the Up main to the Down Main in the Up direction, reversibly signalled, via crossover No.1783 when the train had passed Keymer Junction, but was well south of Haywards Heath. He explained that, as there was an engineers possession of the Up Main line between Keymer Junction and Haywards Heath, he had routed 2A19 at Keymer on to the Down Main line, another reversibly signalled section, and thence into Haywards Heath Station Platform 3.
Meade said that when 2A18 was in the Balcombe area 2A19 had already reached Haywards Heath. He continued to watch the progress of both trains on his panel by the means of the track circuit indications. He saw Track Circuit YG show occupied, indicating that 2A18 had passed signal T335X at danger and soon after 2A19 passed signal T332. Thus the two trains were less than 1,000 yards apart, heading straight for each other. Points 1783 were in the ‘reverse’ position for the route already set for 2A19 and the next indication of movement of the trains was when the points indicated ‘out of correspondence’, showing that they had been run through by 2A18. Finally, the only track circuit displaying ‘occupied’ was YE which indicated that a head on collision had occurred or the two trains had come to a halt within the length of the one track circuit.
Meade said at 02:00 he received a telephone call from signal T 331 from the driver of 2a19 reporting that the two trains had collied head on and requesting that the emergency services should be summoned immediately. He had already alerted Regulator G. de Rosa of the events leading up to the accident and the latter now took immediate action to summon the emergency services.
The driver also asked for the traction current in the area of the accident to be isolated and Meade said that he immediately contacted Three Bridges Electrical Control to arrange the isolation which was granted between Redbridge Sub-Station and Folly Hill Sub-Station at 02:06. Meade said that, together with the signal on the adjacent panels, 4 & 6, the necessary action was taken to protect the scene of the accident. Emergency replacement switches were operated and reminder appliance were placed on panel button where appropriate.
I questioned Meade at length concerning his setting of routes as trains 2A18 & 2A19 approached the reversibly signalled section between Balcombe Tunnel Junction and Copyhold Junction to make absolutely sure that, despite all the approach locking and time delays built into the signalling, he had not altered the route that he had set in front of either train. This was particularly significant as I knew that I was to hear evidence from a leading railman at Haywards Heath that shortly before 2A19 arrived in the section he had note on his train information VDU from Three Bridges that a Down train routed into Platform 2 had been changed to Platform 1. Meade vigorously denied that he had altered t any time the route he had set for either train and reiterated that he had set the route from Haywards Heath Platform 3 to Junction signal T332 and thence through crossover 1783 to the Down Main line in the Up direction all the way up to Balcombe Tunnel Junction well before 2A19 arrived at Haywards Heath station. Even if this had not been the case and the route from Platform 3 had not been altered with the train in the station, no conflicting route could have been set for at least three minutes without 2A18 on the Up line in the Down direction having passed signal T335X RR showing 2 yellows, T335XR showing 1 yellow and T335X at danger.
Regulator G. de Rosa, the regulator in charge of Three Bridges signal Box on the night of the accident, confirmed that Signalman Meade had drawn his attention t about 01:55 to the fact that train 2A18 has passed signal T335X at danger and had run through points 1783, set ‘reverse’, at the same time as train 2A19 had passed signal T332 in the up direction routed through crossover 1783 onto the Down Main line in the Up direction. The first indication of the accident, which he saw for himself was Track Circuit YE occupied and the description of 2A19 shown on the Down line north of crossover 1783, Track Circuit YE was
the only one occupied, while the description of train 2A18 was still in the berth behind signal T335X, indicating that the train had passed the signal at danger. Both trains must have been within the length of Track Circuit YE which could only have resulted in a head-on collision or, if the drivers were extremely alert, the trains might have come to a stand short of actually colliding.
At 02:00 the driver of 2A18 telephoned Meade from signal T331, reporting that his train had collided head-on with 2A19 and requesting that the emergency services be summoned immediately. De Rosa alerted the emergency services using the special number on the Waterloo exchange. He then alerted the various Railway Officers and staff who would be involved in dealing with the accident. At 02:15 the Fire Brigade reported that they were on Copyhold Lane Bridge and were unable to sight the accident. In order to assist them to the site more accurately De Rosa gave them a grid reference of signal T331 which he knew
from the initial call from the driver of 2A18 was immediately adjacent to the scene of the accident. At 02:25 the driver reported again from the telephone at signal T331 that the train 2A19 had a large number of broken windows, jammed doors and suspected buckled under frames. The two front coaches of train 2A18 were badly damaged and the train had split between the second and third coaches. There were injured passengers in both trains, including persons with fractured bones.
I asked De Rosa to summarise the Signal Box Instruction applying to signalling a train over the reversibly signalled lines controlled from Three Bridges Signal Box. He explained that, except where publish in appropriate Operating Notices, reversible working could only be introduced during an emergency on the authority of the Regulator. As far as train 2A18 & 2A19 were concerned, both were booked services on the reversible lines between Balcombe Tunnel Junction and Copyhold Junction. As there were booked services, no permission had to be given to the signalman to set up these routes.
EVENING ARGUS COLLECTION
Driver P.C. Edwards of the Up train said that he booked on duty at 01:05 and was well rested: the 01:35 Brighton to Victoria train was his first working that morning. He took over the train in Platform 4 at 01:20, carried out his train preparation, including a brake test in conjunction with the guard, and departed at 01:35 on receipt of his guard’s bell signal. He was signalled on the Up Main to Keymer, thence over the Down Main line to Haywards Heath due to engineers possession and then back to the Up Main line, running into Platform 3.
After station duties at Haywards Heath he left with signal T340 displaying a single yellow aspect. As he proceeded round the curve to signal T332, protecting Copyhold Junction, he shut off the master controller and coasted, then switching back into series on the sighting signal T332 displaying a double yellow aspect with a position 4 junction indicator, which changed to a green aspect as he approached the signal. Mindfull of the speed restriction over No. 1783 crossover, he at no stage took the controller beyond notch 2 and estimated that his speed was slightly able 20 m.p.h. Edwards said that he first saw 2A18 approaching him as he passed T332. At the same time the Up Main line signal T326 changed from red to green, indicating that 2A18 had cleared the reversibly signalled section from Balcombe Tunnel Junction to signal T335X. A moment latter he saw the driver of 2A18 flashing his cab lights. He immediately made an emergency application of the train’s brakes, released the
driver’s safety device and then dived for cover on the floor of the cross passage between the cab and the passenger part of the coach.
After the collision, Edwards tried to get out of his cab but the doors were jammed. He eventually got out, however, and made his way to signal T331, going between the two trains, which had bounced apart as a result of the collision, and telephoned the
signalman at Three Bridges to inform him of the collision and to request the emergency services be summoned immediately.
Edwards also asked for the traction current in the area of the accident be isolated. He then went back to the heads of the two trains and talked to the driver of train 2A18 who was still unable to get out of his cab, also to driver Pelling who had been travelling as a passenger in 2A18. They took the track circuit operating clips and the short circuit bars from both trains and applied them to both lines. Edwards also sent his guard back to protect the rear of his train, but the guard had badly shaken up by the collision and Edwards was not certain whether he would be able to carry out his protection duties.
Edwards said that he went back into his train, trying to assist the passengers and reassure them that the emergency services were on their way. In order to try to find the emergency services one member of the railway staff walked to Wickham Lane Bridge. Eventually a police car was locate and the emergency services were directed to the scene of the accident via Wickham Lane Bridge. After the emergency services finally arrived, Edwards made his way along the track to Haywards Heath station, looking for his guard. Having satisfied himself that his guard had been taken to hospital Edwards then allowed himself to be
taken there.
Lastly, I questioned Edwards as to what experience he had had with 4 VEP sets skidding when he was braking on the Victoria - Brighton line. Having only been a driver from July 1984, he had very little experience, but earlier in the week of the accident, when he had applied the brakes at Coulsdon South, the train started skidding and when he applied the power on pulling away from Merstham the wheels spun through lack of adhesion. When he found the that the train was skidding he released the brakes to release the wheels and then applied the brakes again, this time more effect. The weather at that time had been wettish and he thought the rails might have beens greasy.
Guard S.M. Nixon the guard of the Brighton - Victoria train, was able to offer very little useful evidence. He remembered working down as the guard of the 22:32 Victoria - Brighton train and changing platform at Brighton to work train 2A19, the 01:35 Brighton - Victoria train. He could not remember making a brake test, nor could he remember leaving Brighton or any of the incidents leading up to the collision or after it. The first thing he remembered was waking up in Cuckfield Hospital, wondering what he was doing there.
Driver E.B. Batchelor a driver since 1976, was the driver of the 01:00 Victoria to Brighton trina, 2A18. After working the 23.15 Brighton to Victoria train he had gone to the Brighton end cab of the 4 car Class 421 unit which was to form the 2A18 and had carried out a brake continuity test in conjunction with guard: the test had been completely satisfactory. The journey had been entirely uneventful as far as Three Bridges where they lost a few minutes due to station duties.
After leaving Three Bridges the wheels lost adhesion for a short period, resulting in wheel spin, but he shut off power and then opened up again which successfully cleared it. He braked without difficulty approaching Balcombe Tunnel Junction before receiving the signal with the necessary route indication for him to cross from the Down line onto the Up line one the Down direction, whereupon he traversed the facing crossover at 20 m.p.h. When his train was completely on the Up line he fully opened the controller and ran without any wheel spin through Balcombe Tunnel and on to Balcombe Station whee closed the controller and commenced to coast at a speed of 65 m.p.h.
Batchelor said that when he sighted the first signal on the reversible section of line, Signal T335XRR which was showing a Double Yellow aspect, he started to brake, applying about 20lb/sq in. on the E.P. brake. He realised that the train’s wheels had locked as speedometer dropped to zero and so he released the brake until he could see that the wheels were revolving, whereupon he made a further application of the E.P. brake of about 20lb/sq in. of air. He clearly remembered that the train was skidding when it was on the Ouse Viaduct and that as he come off it, he freed the wheels by releasing the brakes and then again re-applied them using 20lb/sq in.
Batchelor said that he continued to apply and release the brakes, in the manner he had been taught to brake when encountering low adhesion, each time using 20lb/sq in. of air resulting in the speedometer indicating zero which in turn showed that the train was skidding; after each release of the brakes the speedometer would recommence to register the speed, showing that the wheels were freely revolving. Signal T335XR, showing a Single Yellow aspect, was passed at 40 -45 m.p.h and Batchelor continued to use the ‘brake and release’ method in an attempt to control his train. He continued to do this as he approached Signal T335X at Red which he passed at about 20 -25 m.p.h., having cancelling his A.W.S. as he approached the signal.
I questioned Batchelor about his continuation of the brake and released method after he passed signal T335XRR and approached Signal T335X, pointing out that he knew that the latter signal was approach control to ensure that Down rains on the Up line, did not cross to the Down line via Crossover No. 1784 in excess of 20 m.p,h, I asked him whether he was not expecting that the signal would clear as he approached it and thus was not unduly alarmed at that fact, using his method of braking, it was extremely doubtful if he was going to bring his train to stand before Signal T335X. He assured me that he was endeavouring to bring the train to halt before the signal, that at no time did he assume that it would clear to a proceed aspect as he approached it and that he considered that his method of ‘brake and release’ was the most effective in the condition of low adhesion. In his opinion, if he had made a full emergency application of the brakes as he passed Signal T335X and approached the Up train 2A19, his train would have continued to skid into the other train.
As he approached the other train he flashed his cab lights two or three times as a warning to the driver of 2A19. At the moment of impact the wheels of his train were locked and he recalled being thrown against his desk and then receiving a blow in his back. After the collision he turned the master switch to off and took the key out. He was unable to join Driver Edwards on the ground as his driver’s doors were jammed, but the latter, having ascertained that not injured, took his short-circuit bar, track circuit-clips and detonators, applying the first to the Up line and the second to the Down line. He then managed to open the communicating door to the train and made his way to the rear cab to apply the handbrake. En route he tried to reassure the passengers, a number of whom were injured.
Guard P.D. Norton worked 2A18, the 01:00 Victoria Brighton train. He said that he had an uneventful journey as far as Three Bridges where they lost a few minutes due to the time taken to unload parcels and papers. the train started normally from Three Bridges and he then particularly remembered going through Balcombe Tunnel as the wall nearest to the train was the righthand one, indicating that they were travelling on the Up line in the Down direction, using the reversible signalling. Norton was unable to estimate the speed they were travelling when they emerged from the tunnel. He certainly, however, that the train was not travelling excessively fast and, in his opinion, it was travelling at the normal speed when going on that stretch of reversibly-signalled line.
Norton said he was unable to remember anything from when the train emerged from Balcombe Tunnel until after the collision when he regained consciousness and found himself in one of the passenger coaches together with four or five passengers. A young lady was comforting him he said “because I was in a state of shock and didn’t know where I was”.
Leading Railman A. P. Woodrup was on duty at Haywards Heath Station on the night of the accident. His office was on the Down island platform, facing platform No.2, and to assist him in his platform duties he was provided with a visual display unit (V.D.U.) showing the movement of trains in the Haywards Heath area. He noted from the V.D.U. that the 01:35 from Brighton was travelling Up the Down line from Wivelsfield and was being routed into No.3 platform. He also noted at that time that the V.D.U. first showed the Down train, 2A18 signalled into the UpMain platform, at the end of the platform. This then changed to platform No.1 and then the platform indications for the Down train disappeared completely.
Woodrup then went over to platform No.3 to cary out the platform duties with train 2A19. These duties were entirely uneventful and he estimated that he was only away from his office for about three minutes. When he looked again at his V.D.U. it seemed as though the two train were side by side. At about 02:00 he was sled by the signalman at Three Bridges to go to Copyhold Junction on foot to investigate whether or not there had been a collision. He at once set off along the Down chess to investigate and en route met the guard protection the rear of the Up train: he was very dazed. Woodrup told him to sit at the side of the track as it was obvious that he was in no state to continue his duties. He carried on to the trains, found a guard who had been travelling as a passenger and requested him to go back and complete protection of the Up train. He went through both trains and, finding a considerable number of passengers either injured or suffering from shock, he enlisted uninjured passengers to
help carry out first aid.
Woodrup said that he had then telephoned the signalman at Three Bridges from Signal T326 to inform him of the details of the collision. He then continued onto Copyhold Lane Bridge where he had seen blue flashing lights. Arriving at the bridge, he found no vehicles, but soon afterwards a police car arrived and he informed the officer in charge that there was a considerable number of injuries and explained the location of the two trains, whereupon it was decided to use Wickham Lane bridge for the emergency service to evacuate the casualties. Woodrup then moved back to the trains, helping to remove the passengers and
then helping with the removal of the trains.
Driver A.G. Pelling said that he was travelling as a passenger on 2A18, returning to his depot at Brighton. He had been a driver since 1960 and had been stationed virtually all the time at Brighton. Thus he was a very experienced driver with a comprehensive knowledge of the London - Brighton line. Describing his journey from Gatwick to Copyhold Junction, he said it was quite normal with no excessive speeds, nor any sharp braking until they were approaching Copyhold Junction: he was aware that the train was travelling down the reversibly signalled Up line. He did not notice the train passing through Balcombe Station or over the Ouse Viaduct, as he was talking to his guard, but he was aware that the train was skidding as it approached Copyhold Junction.
Pelling said that he was sitting over a bogie and thus aware of the wheels skidding and then of the sound of the brakes being released. He could not say how many times the driver applied the brakes, the wheels skidded and then the brakes were released before being re-applied, but he was expecting that the skidding would cause wheel flats if it continued and he was waiting for them to develop. He was absolutely certain that each time the brakes were applied the wheels skidded, for the sound of the wheels on the rails when skidding was unmistakable.
When the collision occurred. Pelling was thrown to the floor but, after he had recovered from his fall, he tried to get down on to the track to discover what had happened. The doors in his coach were jammed but he managed to open one in the next coach and then went forward to the head of the train where he talked to both the train drivers, Edwards and Batchelor. The former was concerned about the protection of his train and Pelling and his guard agreed that they would ensured that this was carried out.
When they had finished protecting the train they returned to the drivers where Pelling answered the adjacent signal post telephone and was informed that the emergency services were on their way.
Pelling also asked the drivers whether the short circuiting bars had been applied to give a local protection against the re-energising of the conductor rails. Only one had been put down and so he immediately obtained a second and applied it to the other line, thus ensuring that both Up and Down Main lines were protected electrically.
I asked Pelling about the weather on the night of the collision to which replied “just damp, damp and misty”. finally, in answer to more questions, he agreed that there were a number of areas on the Southern Region where, particularly with heavy freight trains, you tend to get wheel spin on the rising gradients and brakes locking with the wheels skidding on the falling gradients:
Balcombe was one of those bad cases.
Guard H.K. Watson had accompanied Pelling from Gatwick and confirmed the evidence the latter had given. He too telephoned the signalman at Three Bridges to ensure that all the necessary protection had been given, and then went to Copyhold Lane bridge to locate the emergency service where, after about five minutes, the police arrived, announcing that
Wickham Lane bridge would b used for the evacuation of the casualties.
Watson said that he could not comment on train 2A18 as it approached Copyhold Junction, although he was aware that the driver was applying and releasing his brakes. He was unable to estimate the train’s speed as it proceeded towards the scene of the accident but was certain that it was not excessive and that it gradually dropped until at the collision he estimated the speed to be 10 - 20 m.p.h.
Brighton Top Yard
Mr G.R. Taylor, the Regional Traction Inspector, Waterloo, said that he had examined the condition of the running rails on the Up line from Ouse Viaduct to the point of collision on the morning following the accident. The rails at the southern end of the viaduct had some black depots on their heads, but the deposits were intermittent. From the 35 mile 36 chain, point the railheads were black until 36 mile 05 chain, then not as black to 36 mile 15 chain, and finally solidly black from there to the point of the collision at 36 mile 72 chain. Where the railheads were black, there were many trees on the line side which had shed their leaves. Skid marks could be seen at irregular intervals from 36 mile 25 chain to the point of collision. in contrast, the railheads on the down line were clean and bright with o black deposits.
Mr. Taylor said that he observed the passage of the first two train on the Up line in the Up direction after the line was re-opened to traffic. Both experienced bad wheel spin over the section of line he had examined, thus confirming the low adhesion on that stretch of line.
Mr Taylor also examined how a driver recognised when his train was skidding. The speedometer only indicated what the wheels were doing on the driver trailer at the head of the train, but a driver would normally hear a hissing noise and also notice a lower volume noise in general because the noise from the wheels running on the rails ceases. If it was only the front coach that was skidding, the driver would experience ‘bumping and boring’ from the rear coaches. The other important thing to note was that when a driver released the brakes when skidding took place, it took several seconds - sometimes four or five - for the brakes to finally release. Mr Taylor had also notice that wheels did not necessarily start revolving immediately. He also experienced delay of three or four seconds before the wheels started to revolve.
Finally, Mr Taylor confirmed that having hears his evidence, he considered that Driver Batchelor had braked in accordance with the current instructions on the Southern Region in attempting to overcome the poor rail adhesion and bring his train to a halt before signal T335X at Danger.
Cattle Dock Haywards Heath